Numerical on Preliminary Estimate of Buildings and Roads
Er.Anirudh Yadav Tutorial No:-2
#Numerical
on Preliminary Estimate of Buildings and Roads
Q1. Prepare a preliminary estimate of a
building project with a total plinth area of all buildings of 1500 sq m. Given
that-
i) Plinth area rate - Rs. 950.00 per
sq m.
ii) Extra for special Architectural
treatment- 1.5% of the
building cost.
iii) Extra for Water supply and
Sanitary Installations- 5% of the building cost
iv) Extra for internal installations-
14% of the building cost
v) Extra for services- 6% of the building
cost
vi) Contingencies-3%
Vii) Supervision charges- 8%
Q2. Prepare a Preliminary estimate of a
four storeyed office building having a carpet area of 2000 sq m for obtaining
the administrative approval of the Government given the following data. It may
be assumed that 30 percent of the built-up area will be taken up by the
corridors verandahs lavatories, staircases, etc., and 10% of the built up area
will be occupied by walls.
(i) Plinth area rate is- Rs. 1050.00
per sq m
ii) Extra due to deep foundation at
site - 1% of building cost
iii) Extra for special Architectural
treatment- 0.5% of building cost.
iv) Extra for water supply and
Sanitary installations- 6% of building cost
v) Extra for Electric installations-
12.5% of building cost
vi) Extra for other services- 5% of
building cost
vii) Contingencies-2.5%
vii) Supervision charges- 8%
Q3. Prepare a preliminary estimate of a multi storied office building having a carpet area of 1600 m². The circulation area is 30% of the building and 10% is occupied by the wall area. The rate is $ 70 per m².The cost of electricity and sanitary installation is 10% of the building cost. External services are taken as 2% of building cost. Contingencies and supervision charge 4% and 5% of overall cost respectively.
Q4. Prepare a preliminary estimate of a building having a plinth area equal
to 1600 square meters.
Given that
i. Plinth area rate= $ 200 per m²
ii. Extra for
architectural work= 1 ½ % of building cost
iii. For
electrical installation= 10% of building cost
iv. For water supply and sanitary installation=
5% of the overall cost
v. Contingencies and supervision charge 4% and 5% of overall cost respectively
Q5. Find
the preliminary estimate of the road having a length of 10 km. The width of the
road is 8 m and the thickness is 0.2 m. The rate per km for the given road is
8,000$. Take 10 to 30 % of the overall cost for supervision and
technical services
Q6. Prepare a preliminary estimate of a multi storied building having a carpet area of 2200 sq. m. 22% of the built up
area will be taken up by corridors, veranda, staircase etc. and 14% of built -up
area will be occupied by walls.
*Note:-Assume the
plinth area rate Rs. 16,000/- per sq. m. and provide for water supply and
sanitary fitting and electrical installation, contingencies and other services.
Q7. Prepare an approximate estimate of building project with total plinth area of all building is 80 sqm. and from following data.
Plinth area rate Rs. 40000 per sqm .
Cost of water supply @ 7½%of cost of building
Cost of Sanitary and Electrical installations each @ 7½% of cost of building
Cost of architectural features @1% of building cost.
Cost of roads and lawns @5% of building cost.
contingencies @ 4%
Determine the total cost of building project?
Q8. Prepare the rough estimate for a proposed commercial complex for a municipal corporation for the following data.
Plinth Area = 500m2 /floor
Ht. of each storey = 3.5m
No. of storey’s = G+2
Cubical content rate = Rs. 1000/m3
Provided for a following as a percentage of structured cost water supply & Sanitary arrangement-8% Electrification -6%
Fluctuation of rates - 5%
Contractors profit - 10%
Petty supervision & contingencies- 3%